Project Reviews 

1st Review  - 4 weeks 

City staff reviews the project submittal for compliance with the Westminster Municipal Code (W.M.C.), existing ODPs, and other Design Guidelines.  

Referrals to partner agencies and stakeholders may be issued and comments integrated into Staff Review comments.

Neighborhood meeting(s) may be required.

Comments and Redlines Issued - Staff issues comments and redlines to owner and applicant (per project application) through the project review number assigned through the online permitting manager.  If you have any questions regarding the comments and redlines regarding your project, please contact your Project Planner. 

Applicant Revises Project - 

  • Address the comments from staff review.
  • Submit revisions 
2nd Review - 3 Weeks 

Comments and Redlines Issued - Staff issues any repeat comments and redlines to owner and applicant (per project application) through the project review number assigned through the online permitting manager that were not addresses or negotiated through the first review process.  If you have any questions regarding the comments and redlines regarding your project, please contact your Project Planner. 

Applicant Revises Project - 

  • Address the comments from Staff review.
  • Submit revisions 
 Subsequent Reviews - 3 Weeks 

Additional reviews may occur if comments are not addresses or new items are added during the review process.