Homepage > News

News

Monday, May 24, 2021

Asbestos abatement, demolition at 7287 Lowell Blvd. and 3630 W. 73rd Ave.

Project Scope

  • Abate the asbestos located in the exterior and interior of both buildings. All asbestos abatement activities are in accordance with Colorado Department of Public Health & Environment (CDPHE) regulations, permitting, and guidance.
  • Asbestos abatement will require the buildings to be tented and a generator to be on at all times for the extent of the work (estimated two weeks).
  • Demolish both buildings after certification from CDPHE that the asbestos abatement is complete.
  • Disconnect water and sanitary sewer service lines.

Timeline

Asbestos abatement will begin in June 2021. Demolition and site clean-up will start sequentially in July 2021. All work is expected to be complete in July 2021.

Current Work

The project team has obtained all necessary permits from CDPHE to start the asbestos abatement.

For more details, contact: Seth Plas at (303) 658-2096, or visit: www.westminstereconomicdevelopment.org/housing/cdbg

Number of views (25433)/Comments ()

Recent News

1345678910Last
All Articles

Newsletter Sign-up