72nd Ave. Planter Box Renovation Project

The planter boxes along the 72nd Avenue and Federal Boulevard corridors will be renovated to re-establish a more aesthetically pleasing landscape through the use of xeric, drought tolerant, and native plant material. These plantings will provide flowering and color throughout the growing season, which will beautify and rejuvenate this highly-traveled corridor.

Timeline: The renovations are estimated to start on April 8, 2024, with an estimated completion of Fall 2024.

Scope: 177 planter boxes along 72nd Avenue from Eliot Circle west to Meade Street and along Federal Boulevard from 74th Avenue to 72nd Avenue will be renovated. This will involve replacing dead plant material and empty planters with xeric plantings and a layer of rock mulch.

Traffic Impacts: Drivers can expect sporadic lane closures throughout the duration of the project. Please follow all directional signage in the area.

 

 

Sherwood Park: CONSTRUCTION UPDATE

The new playground equipment has been installed, the rubberized surfacing will be installed next week.  Once the fencing has been removed, the playgrounds are open for use

On June 24th, a City contractor will be on site to resurface the basketball court at Sherwood.  Construction should last no more than 2 days, the court will be closed for use until the surface has cured. 

 

 

Trailside Park: CONSTRUCTION UPDATE  

Installation of the new playground equipment will begin on Monday, April 29thInstallation of the new equipment will take approximately 3 weeks

 

 

 

 

 

Somerset Park: CONSTRUCTION UPDATE  

The new playground equipment has been installed and we are awaiting new rubberized surfacing.


 

 

 

City Park Tot Playground (Child Care): CONSTRUCTION UPDATE  

This project has been completed!