Home > Residents > Roads & Construction > Cone Zone > Sheridan Boulevard, 80th Avenue to 88th Avenue - Utility Work

Sheridan Boulevard, 80th Avenue to 88th Avenue - Utility Work

Project Update:

over 80% complete with Sheridan Boulevard utility construction

  • During nighttime construction sanitary sewer pipe replacement continues  Sheridan Boulevard south of 84th Avenue in Sheridan Boulevard. right-of-way between 84th Avenue and Sheridan Boulevard.
  • Water main construction is happening on across Sheridan Boulevard north of the Sheridan Boulevard and 84th Avenue intersection.
  • Daytime construction activities are focused on asphalt pavement patch back in Sheridan Boulevard, as well as curb and gutter replacement.
  • Nighttime water main construction in the intersection of Sheridan Boulevard and 84th Avenue is scheduled for completion by the end of the following week, June 29.
  • Once water main construction in the intersection of Sheridan Boulevard and 84th Avenue is complete, water pipe replacement will continue outside of Sheridan Boulevard roadway in the west right-of-way area.
  • Final asphalt trench paving north of 84th Avenue will be scheduled in July, after the water pipeline is replaced and passes inspection. 
  • Temporary pavement patch will remain in place into the month of July north of 84th Avenue in Sheridan Boulevard.
  • Concrete sidewalk and curb repairs on Sheridan Boulevard are ongoing.

Traffic Impacts

  • As pipe is being installed left turns across traffic on Sheridan Boulevard will be restricted in some areas for the public’s and contractor’s safety.
  • Uneven and rough road surfaces will remain in Sheridan Boulevard temporary pavement areas into the month of July.
  • Northbound and southbound Sheridan Boulevard traffic will be restricted to one lane between the hours of 8:30 a.m. and 3:30 p.m. for the public’s and contractor’s safety.
  • Detours will be provided and traffic through the intersection will be restricted for the contractor’s and the public’s safety.
  • Nighttime construction between the hours of 7:30 p.m. and 5:30 a.m. is scheduled the week of June 11 - 29. 
  • Two lanes of traffic will be maintained in both directions on Sheridan Boulevard during heavy commuter traffic periods.
  • Speed limits will be reduced and enforced in Sheridan Boulevard for public and worker safety.

Pedestrian Crosswalks

  • Pedestrian crosswalks on Sheridan Boulevard are open at 88th Avenue, 84th Avenue, 81st Place and 80th Avenue.
  • During nighttime construction pedestrian crosswalks at 84th Avenue and Sheridan Boulevard are restricted.

Project Details

The city has been coordinating the replacement of aging utility infrastructure in the areas of Sheridan and 88th Avenue for many years. Various projects have been completed including CDOT improvements to the Sheridan bridge over U.S. 36, expansion of U.S. 36 and the addition of various water and storm sewer utilities. More recently, improvements have been made within the westbound lanes of 88th Avenue in conjunction with the new Downtown Westminster construction.

  • Replacement of a water transmission main in Sheridan Boulevard (88th to 80th Avenues) - this is a large water main that serves vast areas of south Westminster.
  • Replacement of a wastewater pipeline in Sheridan Boulevard (88th to 80th Avenues) - this is a large sewer pipeline that serves the southern third of the city.
  • Asphalt patching and paving of the streets - in conjunction with pipeline work, streets will be repaired and resurfaced to address age and condition issues.
  • Customer connections – this work will involve connecting existing city customers to the new pipelines. The work will be sequenced to limit service interruptions to the maximum extent possible.

New construction will enhance the reliability of the water distribution and sewer collection systems, improve fire protection and emergency response capabilities, and provide capacity for city growth.

Timeline

  • Late January 2017– Mid-November 2017: Water and sewer construction in Sheridan Boulevard and 88th Avenue (south to the railroad).
  • Late January 2017 – September 2018: Water and sewer pipeline construction in Sheridan Boulevard right-of-way from 88th Avenue to 80th Avenue.

Construction for the project will be sequenced to help maintain access to businesses. Typical pipeline construction will progress at 20-40 feet per day. Portions of the construction must happen sequentially, so Sheridan Boulevard and portions of 88th Avenue will see construction more than once.

Intersection closures will target night time construction to minimize the impact to commuters and to improve safety for the public and contractors working on site. The project will focus on keeping two lanes of traffic open in both directions on Sheridan Boulevard during high traffic volumes and a minimum of one lane of traffic open in both directions on 88th Avenue.

These projects are funded from the Utility System Capital Improvement Project budgets and will allow the city to maintain a high level of services now and into the future.

Information/Questions

For more information, contact Senior Engineer Stephanie Bleiker, PE. at 303-658-2174 or sbleiker@cityofwestminster.us.